Docket 26-06-17
Petition for Approval of Method and Manner of Construction and Permission to Energize the Haddam Substation to East Haddam Junction Rebuild Project (1772 AND 348 LINES)
Decisions and notices3
What the Authority has issued in this docket, newest first.
Documents filed to open the docket1
Haddam_EHJ_PURA_ Petition.pdf
PDF · 6.1 MB · 16 pagesText searchable
Filings4
1 filing of the selected types
About this docket
- Docket number
- 26-06-17
- Status
- Closed August 12, 2026
- Type of matter
- General Matters
- Filed by
- CL&P dba Eversource Energy
- Submitted by
- Eversource Energy
- Date filed
- June 26, 2026
- First filing
- July 17, 2026
- Latest filing
- August 12, 2026
- Public filings
- 4
- Documents
- 6 (6.6 MB)
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised August 5, 2026
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.